- When installing this option, turn OFF the main power and unplug the power cord from the wall socket. If installing without turning OFF the main power, an electric shock or a malfunction may occur.
Before installing this option, attach the “Bridge Unit BU3070 (D685)” or "Internal Multi-Fold Unit FD3000 (D3E4)"first.
Attach the “LCIT PB3170/ PB3230 (D695)” or “Paper Feed Unit PB3210/PB3220 (D787)” first before installing this option.
This finisher is light and has a high center of gravity, so it easily topples when installing or moving it. Therefore, it is equipped with the stabilizer [A] attached to it when shipped.
- When you lift the finisher at the time of unpacking, do not hold the part [A]. Doing so may damage the frame.
After unpacking, immediately attach the stabilizer [B] to prevent toppling.
Push it in thoroughly along the guide [A] until it clicks.- Remove the external orange tape and shipping retainers.
- Open the front cover, and then remove the orange tapes and shipping retainers.
- Remove the accessories in the package (fixing screws, etc.).
Remove the fixing brackets of the stapleless stapler unit. (
Be careful not to touch the encoder [D] at the back of the motor.×4)
Remove the fixing brackets in the order of [A], [B], and [C].
The fixing brackets are hooked to the metal plate, so slightly lift it and then remove it.
Be careful so that the fixing brackets do not come into contact with the feedout pawl HP sensor.
If they come into contact, check that the feeler [B] is positioned correctly.- Attach the shift tray [A] (
x1; M4 x 8).
- Attach the entrance guide plate [A]. (M3 x 6)
- Clean the right side of the upper cover with a cloth moistened with alcohol, and then attach the cushion to the finisher.
- Make sure that the cushion is aligned with the left-upper edge [A] of the upper cover.
If the internal multi-fold unit is installed on the main machine, the cushion is too long. So cut off a section of the cushion at the notch in the cushion, so that the cushion does not interfere with the I/F connector [A] of the finisher.
- Attach the ground plate [A] (M3×6).
Attach the joint bracket [A] to the main machine (M4x12).
If the machine is equipped with the bridge unit, attach the joint bracket [A] together with the L type connecting bracket [B] of the bridge unit.
If the machine is equipped with the internal multi-fold unit, attach the joint bracket [A] only.- Attach the screw so that the screw head is at the center of the mark.
- Attach the screw so that the screw head is at the center of the mark.
- Connect the cable of the finisher to the connector of the Internal Multi-Fold Unit. (Only when the Internal Multi-Fold Unit is installed.)
- Remove the screw on the connection lever [A] and pull the lever.
- Connect the finisher to the main unit, and then push in the connection lever [A] to fasten it to the main unit.
When the Internal Multi-Fold Unit is installed, check that the two cables of the finisher do not cross each other, before connecting the finisher (for interference prevention). - Connect the interface cable [A] to the machine. (Only when the Bridge Unit is installed.)
- Close the front cover.
- Turn ON the main power.
- Deliver some A3/DLT paper to the proof tray and check if the vertical registration is correct according to the adjustment scale for A3/DLT paper. (Finisher Registration Adjustment)
- Check that the finisher can be selected on the operation panel, and check the finisher’s operation.